Spring Hill Froze Its Sewer Taps, So Why Are Homes Still Going Up?

At June Lake, on Spring Hill's northeast edge, Signature Homes has 75 lots in Pod E Section 3 and sewer capacity for 14 of them. A city staff memo dated November 2, 2026, recommended letting the builder put in infrastructure and final-plat all 75 anyway, at its own risk, with no wastewater connection authorized for the other 61. The item went on the Board of Mayor and Aldermen's November 2 agenda as a work-session discussion.

The city has been under a sewer moratorium since January, and homes are still being permitted, framed and sold. The city had already committed sewer capacity to projects before the freeze.

The freeze and the backlog of sewer commitments

On January 5, 2026, the Board of Mayor and Aldermen unanimously passed Ordinance 25-29 on second reading, as the Columbia Daily Herald reported. According to Spring Hillian's explainer, the ordinance freezes new sewer taps for new development and holds back a 100,000-gallon-per-day reserve that the board can hand out case by case.

The city imposed the moratorium on itself. It followed a consent order from the Tennessee Department of Environment and Conservation, case WPC2025-0093, over problems at the water reclamation plant on Mahlon Moore Road. By 2025 that plant had nitrogen discharges far above permitted levels, broken solids-handling equipment and wet-weather bypasses.

A September 2025 city list totaled outstanding sewer commitments at 9,100 more homes, 13.7 million square feet of commercial space and 1,498 hotel rooms. At a June board meeting, the city's water team described the size of that backlog plainly, as Spring Hillian reported:

The city "has already committed to more development capacity" than even the first round of the $320 million rebuild provides, "so we will be working for probably fifteen years straight to program things until we hopefully can get to a point where we feel like we've caught up."

Permits fell, and vested projects kept them from stopping

The building numbers show how this plays out. By October 2025, after the city had briefly stopped accepting new development applications, Spring Hill issued just two single-family, townhome and condo permits for the whole month. Then in August 2026, with the moratorium in force, the city issued 45 of them, 20 on the Maury County side and 25 on the Williamson County side. By the end of August, 214 single-family permits had been issued year to date, according to the city's August building codes report.

That pace is real, but it comes from a narrow set of places. Saddlewalk at June Lake is one of them. Spring Hillian's June Lake development tracker found a steady stream of single-family permits on Marston and Saint Clair Avenues in July, for homes of about 3,800 square feet with construction values around $630,000. June Lake held 2,926 committed homes on the September 2025 list, with 2,579 still to build.

For a buyer shopping new construction, this changes what comparing options means. The city administrator has described permits as being at "new lows." The new homes that do get built come mostly from master plans that locked in capacity years ago. Shopping a new home in Spring Hill now mostly means shopping a short list of vested projects and their builders.

The wait shows up in the shopping trip

Homes and businesses come out of the freeze very differently. As of the September 2025 sewer list, June Lake was about 12% built on homes and essentially 0% built on commercial space. That's 1.28 million square feet of retail and restaurant space and 3.9 million square feet of office still ahead. Pod K, the first business cluster on June Lake Boulevard east of Buckner Lane, now has buildings going up.

Project Location Where it stands in early November 2026
Liberty Federal Credit Union 2600 Buckner Lane Under construction, builder targets summer 2027
Heartland Dental 3030 June Lake Boulevard Under construction, about 5,000 square feet
June Lake Collective 3060 June Lake Boulevard Two buildings permitted, completion targeted summer 2027, restaurant space capped near 9,000 square feet by sewer allocation
Image Studios 3070 June Lake Boulevard Original summer 2026 opening target has slipped
Sprouts Farmers Market Duplex Road and Port Royal Road No site plan on a Planning Commission agenda through October 26, 2026, and no building permit

The June Lake Collective shows the mechanism most clearly. Its restaurant space is capped by gallons, not by demand. When Brentwood-based GBT Realty announced the Sprouts project in October 2025, it said, as Spring Hillian recounted, construction would start in early 2026 "with City approvals" and the store would open in early 2027. The moratorium began that same January. Spring Hillian's November 2 report notes that a grocery store needs a sewer connection and that the city isn't handing out new ones. Hy-Vee's planned store at Buckner Lane and June Lake Boulevard hasn't moved through City Hall since 2023.

Businesses that are already open feel the freeze too. Nelly's Italian Cafe has been in town for seventeen years and wanted to expand into the vacant shop next door, adding about sixteen seats. The ordinance scores restaurant seats at 35 gallons a day each from design tables. An engineering memo put the real added flow at about 263 gallons a day. The board settled it with Ordinance 26-17, adopted on second reading October 5, 2026, which grants Nelly's 460 gallons per day from the discretionary reserve. Adding sixteen seats took a board ordinance.

The resale market and new construction

The resale market moves with the wider market. Across Greater Nashville REALTORS' nine-county area, which includes Williamson and Maury, residential closings in October 2026 had a $499,990 median price and averaged 61 days from listing to contract.

New construction is where the freeze turns into paperwork. A city staff memo recommended letting the builder put in infrastructure and final-plat all 75 lots in Pod E Section 3, although sewer capacity was available for only 14 of them. Expected dates for nearby shopping are also worth weighing against the actual permit and site-plan record, not the announcement.

Amenity timing matters for buyers who are paying for a location.

The dates that decide when it loosens

There's no announced end date for the moratorium. These are the milestones on the calendar, roughly in order:

  1. Buckner Lane's final widening phase. The city expects the full five-lane road, with trails and sidewalks, to open later in 2026, running from Thompson Station Road near June Lake down to Duplex Road.
  2. The Columbia connection. On October 19, 2026, the board unanimously approved Resolution 26-302, an interlocal wastewater plan with Columbia. It calls for a 12-inch main along Mahlon Moore Road and a TVA easement that would carry 500,000 to 1.5 million gallons per day once complete, according to the city's announcement. Spring Hill Daily reported that the line runs about 23,600 feet and still needs TDEC approval.
  3. June Lake Trail. Construction plans for a paved one-mile loop around the lake, with a scenic overlook, are awaiting permits, and opening is expected in spring 2027. Quarterly public tours of the historic Pointer Cemetery, through an agreement with the Battle of Franklin Trust, are expected to launch in 2027.
  4. The plant rebuild. The roughly $320 million overhaul of the water and wastewater system is targeted for final commissioning on May 27, 2030.

The plant itself is improving. Its nitrogen discharge dropped from about 95,000 pounds a month in April 2025 to about 24,000, and in August the board voted 9-0 to cancel a standalone $25 to $28 million centrifuge project and fold the work into the larger rebuild. The city said that decision doesn't change the moratorium's timeline.

FAQ

Why is construction still happening if new sewer taps are frozen? The September 2025 city list included outstanding sewer commitments to projects made before the freeze, including June Lake. The city issued 45 single-family, townhome and condo permits in August 2026.

If you're weighing a new build in Spring Hill against a resale home elsewhere in Williamson County, Roten Partners can help you compare homes. You can start with our buyer's guide or request a consultation.